Al Narjis Residential Compound
24 residential units on a single plot, handed over in three phases
Private OwnerAl Narjis, Riyadh2025



Design vs. Delivered
Drag the handle to compare the pre-construction 3D visualisation with the built result — same camera angle.


Project Data
Client
Private Owner
Date
2025
Location
Al Narjis, Riyadh
Category
Residential
Status
Handed Over
Duration
26 months
Consultant
Al Mada Engineering Consultants
About the Project
A four-building, four-storey residential compound delivered under a single contract from excavation through final handover. Work was split into three phases so the first buildings could be handed over and occupied while the last remained under construction — letting the owner begin leasing seven months before overall completion.
The Challenge
The site was bounded on three sides by occupied residential buildings, with municipal restrictions on working hours and a midday ban on impact work.
Engineering Solution
Noisy activities were rescheduled into a morning and an evening window, and prefabricated steel formwork cut on-site pour time. Breaker excavation along the neighbouring boundary was replaced with diamond saw cutting.
Scope of Work
- 01Excavation, backfill and deep foundations
- 02Reinforced concrete structure for four buildings
- 03MEP works and central air conditioning
- 04Full interior finishing for all units
- 05Site works, parking and landscaping
Project in Numbers
18,400
m² built-up
24
residential units
4
buildings
26
months to deliver