Corporate HQ Fit-Out — Olaya
Three office floors fitted out while the building stayed occupied
Private sector companyOlaya, Riyadh2023


Project Data
Client
Private sector company
Date
2023
Location
Olaya, Riyadh
Category
Finishing
Status
Completed
Duration
7 months
About the Project
Fit-out of three office floors inside an occupied building, covering glazed partitions, suspended ceilings, and the redistribution of lighting and HVAC to a new functional layout.
The Challenge
The building remained occupied throughout; any dust or noise reaching the other floors meant a work stoppage.
Engineering Solution
The work zone was sealed behind airtight hoardings under negative pressure, and all cutting and demolition moved outside business hours.
Scope of Work
- 01Gypsum and glazed partitions
- 02Suspended ceilings and lighting systems
- 03HVAC outlet redistribution
- 04Flooring, painting and joinery
Project in Numbers
2,900
m² fitted out
3
floors
7
months to deliver